Phase II Sewage Treatment Station Odor Control Project of Chemical Company
Project introduction: This project is the second-phase project of our company’s chemical industry customers. The main construction projects include the odor treatment device of the sewage treatment station, using the equipment provided by our company.
Description
Project Name: Phase II Sewage Treatment Station Odor Control Project of Chemical Company
Gas Flow:35000m³/h
Equipment Used:
Activated Carbon Adsorption and Desorption System,
Spray Column.
Emission Standards:
“GB14554-1993”
Hydrogen Sulfide ≤0.06kg/h,
Ammonia ≤0.6kg/h,
Trimethylamine ≤0.15kg/h,
Methyl Mercaptan ≤0.006kg/h,
Methyl Sulfide ≤0.06kg/h,
Styrene ≤3.0kg/h,
Dimethyl Disulfide ≤0.15kg/h,
Carbon Disulfide ≤1.5kg/h,
Total Non-methane Hydrocarbons ≤40mg/m3